C_PRPS_ART - PS: Project type authorization for WBS elements
BAL Application Log Documentation RFUMSV00 - Advance Return for Tax on Sales/PurchasesThis documentation is copyright by SAP AG.
Definition
You can use this authorization object to control who can access WBS elements in the Project System depending on the
The system checks the authorization:
- during maintenance (editing transactions)
- during display
Defined fields
The authorization object contains the following fields:
- Project type of the WBS element
- Action
The following values are used for the actions:
- 01: Create
- 02: Change
- 03: Display
- 20: Create actual dates
- 21: Time scheduling
- 22: Display dates
- 23: Plan costs
- 24: Display costs and vendor payments
- 25: Plan revenues
- 26: Display revenues and customer payments
- 27: Create budget
- 28: Display budget
- 41: Assign PS text
- 45: Change project number
Examples
User A may change the WBS element L400/10 with the project type IV as well as plan dates and costs. Relevant authorizations:
- Project type: IV
- Actions: 02, 21, 23