New displays and display functions on the planning tables.

Description

For Release 4.0A the following new functions are available for capacity leveling on the capacity planning table:

  • Define properties of the shift calendar
Since 3.1H you can display the shift calendar for a capacity on the capacity planning table. The properties of the shift split and of the time fence are defined in the SAP standard.
In 4.0A you can define the properties of the shift split and of the time fence in Customizing for the time scale profile. See Define time scale profile.
In the SAP standard the time fence is blue. It is continuous in the line of the capacity whose shift calendar is shown and in the other lines of the chart it is dotted.
You can also specify that when the capacity planning table is called up the shift calendar of the fist capacity is automatically shown.
  • Display multiple commitment
Until now you could display multiple commitment at a work center using multiple commitment -> Show.
As of Release 4.0A multiple commitments can also be displayed by marking the objects concerned. In the SAP standard this is a green line at the bottom edge (graphical object type O1). If you want to choose another marking you must enter the graphical object type to be used to display the multiple commitment in Customizing for chart sequences. See Define chart sequence.
  • Change time scale
In the capacity planning table you can change the time scale using Settings -> Scale. Several scales are available that use the following SAP standard profiles.
  • SAP_M011 (Standard hourly split)

  • SAP_M022 (Standard daily split)

  • SAP_M032 (Standard weekly split)

  • SAP_M041 (Standard monthly split)

  • SAP_M051 (Standard yearly split)

These must therefore exist in the client.
  • Position time axis
With Edit -> Position on time axis you can position the time axis in the capacity planning table on the
  • current date

  • date that you enter

  • start of the first graphical object in a selected line

The time scale is positioned in such a way that the selected date or graphical object appears on the left side of the diagram section.
  • Hide work times
You can specify in Customizing that when you call up the capacity planning table the non-work periods are hidden that are common to all capacities (the intersection of all non-work periods). See Define scale of time scale.
  • Switch between current view and overall view
You can switch between the current view and the total view of the Settings -> View -> Adjust diagr.section.
  • Zeitprofil im Einstiegsbild des Kapazitätsabgleichs ändern
Sie können im Einstiegsbild des Kapazitätsabgleichs das Zeitprofil ändern. Wählen Sie dazu Einstellungen -> Zeitprofil ändern. Im Dialogfenster Zeitprofil ändern werden die Daten des aktuellen Zeitprofils angezeigt und können geändert werden.

  • Material data in table section of planning table
You can copy any fields from the material master to the table section of the planning tables. The fields come from the material master. For this purpose there is now the structure MARA for the sort layout key in Customizing for capacity leveling.
  • Insert date markers
On the capacity planning table you can use Edit -> Insert date marker to insert date markers and then delete them again. A date marker is a vetical line that marks a date on the time axis.
To insert date markers in the capacity planning table go into Customizing for the Capacity planning table under Define chart sequence and go to chart position and enter a color category for the date marker.
  • Select operations by drawing a framework
You can select operations on the capacity planning table by drawing a frame around the graphical objects keeing the left mouse button pressed down.
  • Selecting or highlighting operations that belong together
On the capacity planning table you can select or highlight operations that belong together, for example, operations with the same material number. To do this select an operation and choose Edit -> Select or Highlight -> Objects belonging together. All operations are selected that, like the operation selected, have the features specified using the selection fields in the selection key.
Selection keys are, like sort keys, created in Customizing for capacity leveling under Define sort key.
You can enter the sort key
  • in the selection profile

In the SAP standard the first field of the selection key is automatically the selection field
  • online in the capacity planning table with Edit -> Select or Highlight -> Selection

You can choose the selection fields in the selection key. If you also enter values for the selection fields then all of the operations with values are selected.