APO-PPS-OPT: Handling Planned Delivery Time in Optimization ( RELNAPO_30A_SP4_PPS_OPT1 )
Vendor Master (General Section) BAL Application Log DocumentationThis documentation is copyright by SAP AG.
Short text
APO-PPS-OPT: Handling Planned Delivery Time in Optimization
Use
Up to now, the planned delivery time of external procurement orders (purchase orders and purchase requisitions) was not considered during optimization. This meant that material procurement problems could occur in optimized planning.
As of Release 3.0A (First Customer Shipment and Support Package 4), you can configure the system when calling optimization or in the optimization profile that the planned delivery time is considered during optimization.
Effects on Existing Data
Effects on Data Transfer
Effects on System Administration
Effects on Customizing
Further Information