Introduction of the Campaign Status (New) ( RELNAPO_310_PPS_PCM2 )

Introduction of the Campaign Status (New) ( RELNAPO_310_PPS_PCM2 )

Fill RESBD Structure from EBP Component Structure   BAL Application Log Documentation  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

Introduction of the Campaign Status (New)

Use

As of SAP APO 3.1, there is not only an order status but a campaign status, too. It is derived from the statuses of the orders contained in the production campaign. The following statuses have been defined:

  • Created
    The production campaign contains:
  • Only orders that have not yet been released or started

  • No orders

  • Released
    The production campaign contains at least one released order but no order that has been started.
  • Started
    The production campaign contains at least one order that has been started.

In Customizing for Production Planning and Detailed Scheduling under Global Settings -> Maintain Global Parameters and Defaults, you can specify the following depending on the campaign status:

  • Whether or not orders may be removed from the campaign
  • Whether or not a campaign may be dissolved

By making the following settings, you can control that orders must not be removed from a campaign and that campaigns must not be dissolved:

  • No Restriction - this means the campaign status is not taken into account
  • No Released Orders - this means if the campaign contains one released order
  • No Orders that Were Started - this means if the campaign contains one order that has been started
  • No Released Orders or Orders that Were Started - this means if the campaign contains one released order or one order that has been started

These Customizing settings are taken into account in the following planning transactions:

  • When rescheduling manually
  • In the detailed scheduling planning board

  • In the campaign transaction

Effects on Existing Data

Effects on Data Transfer

Effects on System Administration

Effects on Customizing

To make these settings, go to Customizing for SAP Advanced Planner and Optimizer and choose Supply Chain Planning -> Production Planning and Detailed Scheduling -> Global Settings -> Maintain Global Parameters and Defaults. Select the setting you want to use in the Remove Orders from ProdCampaign field.

Further Information

For more information on new and enhanced functions in campaign planning, see Planning of Production Campaigns in PP/DS (New).