Finiteness Level of Resources (new) ( RELNAPO_401_PPS_CRES_FIN )
ABAP Short Reference BAL_S_LOG - Application Log: Log header dataThis documentation is copyright by SAP AG.
Short text
Finiteness Level of Resources (new)
Use
If you want to schedule a resource either finitely or infinitely in different applications, you can control this as of SAP APO 4.0 using the finiteness level at the resource and in the settings for each application.
You assign a fixed finiteness level to the resource in the master data. In the settings for the application, you define the maximum finiteness level up to which resources can be scheduled finitely.
Effects on Existing Data
Existing resources, for which the finite scheduling indicator is set in the master data, are assigned the finiteness level 0 as standard; that is, the resource is scheduled finitely in all applications.
In the SAP standard strategy profile SAP001 for the DS planning board and in the SAP standard optimization profiles, the maximum value 9999 is defined as the finiteness level, which means that all resources for which the finite scheduling indicator is set are scheduled finitely.
In all other existing strategy profiles and optimization profiles, the value is initial at first.
If you assign a finiteness level (> 0) to an existing resource that is flagged as finite, you also have to adjust the finiteness level in the settings (heuristic settings, strategy profiles, or optimization profiles) of the applications that scheduled this resource finitely until now, if you want these applications to continue scheduling the resource finitely.
Effects on Data Transfer
Effects on System Administration
Effects on Customizing
You define finiteness levels in Customizing under Advanced Planning and Optimization -> Master Data -> Resource -> Define Finiteness Levels for Resources.
Further Information
General Material Data Addresses (Business Address Services)