Changing and Fixing Orders in Interactive Planning (Enhanced)

Use

Before now, orders for key figures such as Distribution Receipts (Planned) and Production (Planned) could be changed manually and fixed for subsequent planning runs.

As of SAP APO 4.0, you now have more options for changing and fixing orders in interactive Supply Network Planning.

Changing orders

In addition to being able to change orders in the Distribution Receipts (Planned) key figure, you can now also change orders in the Distribution Demand (Confirmed) key figure, which means you can change deployment stock transfers resulting from a deployment run. The system checks the available-to-deploy quantity (ATD quantity) and informs you if there is insufficient quantity available. You can also choose the destination location from a list of relevant locations. You also have the option of moving deployment stock transfers from one transportation lane to another.

You are now able to assign another production process model (PPM) to an existing planned order in the interactive Supply Network Planning detail view. However, you can only do this for unfixed planned orders. In the interactive Supply Network Planning capacity view, if you move a planned order from one resource to another, the PPM is changed to that of the new resource.

You can also move planned orders from one bucket to another using a context menu. When doing this, the entire order quantity is moved to the other bucket, which means it is not possible to move partial quantities or to distribute order quantities over several buckets. You can move the order quantities within a resource or also from one resource to another.

Fixing orders

In addition to being able to fix and unfix an individual order from a context menu or the interactive Supply Network Planning detail view, you can also now fix and unfix all orders in a specific time period (by highlighting the start and end buckets). All existing orders in this period become fixed or unfixed. However, you can still create additional orders in this period.

In addition, you can select several location products using the drilldown function and then fix or unfix the orders for the selected products and a specific time period.

Effects on Existing Data

Effects on Data Transfer

Effects on System Administration

Effects on Customizing

Further Information






Fill RESBD Structure from EBP Component Structure   ROGBILLS - Synchronize billing plans  
This documentation is copyright by SAP AG.

Length: 2795 Date: 20240423 Time: 083952     sap01-206 ( 54 ms )