Subcontracting with Source Location in SNP (New) ( RELNAPO_401_SNP_SUBCONTR )

Subcontracting with Source Location in SNP (New) ( RELNAPO_401_SNP_SUBCONTR )

rdisp/max_wprun_time - Maximum work process run time   SUBST_MERGE_LIST - merge external lists to one complete list with #if... logic for R3up  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

Subcontracting with Source Location in SNP (New)

Use

As of SAP APO 4.0, you can also plan the subcontracting process with a source location in Supply Network Planning (SNP). Until now, this function was only available in Production Planning and Detailed Scheduling (PP/DS). Subcontracting refers to the process whereby a product is manufactured by an external supplier.

For example, screw manufacturers manufacture screws in their own plant. However, the screws are packed by an external service provider (a subcontractor). The screw manufacturers provide the subcontractor with the screws and the packaging. The subcontractor packs the screws and delivers the packaged screws back to the screw manufacturers.

During screw manufacture, the subcontracting component packaging is managed as part of the stock on hand at the manufacturer for legal and cost accounting purposes. During goods receipt of the purchase order for the packaged screws, consumption of the subcontracting component is posted at the screw manufacturer.

When modeling master data, you have to consider the following:

For each subcontracting component that you want to send from the plant to the subcontractor, you have to manually create a transportation lane from the plant (start location) to the subcontractor (destination location) in the SAP APO system. You also assign the corresponding external procurement relationship to each transportation lane.

Effects on Existing Data

Effects on Data Transfer

Effects on System Administration

Effects on Customizing

In order for SNP orders to be transferred to the SAP R/3 system, you have to make the relevant setting in Customizing. To do this, choose SAP Advanced Planner and Optimizer -> Supply Chain Planning -> Supply Network Planning -> Basic Settings -> Configure Transfer to OLTP Systems.

Note the following:
If you do not configure this transfer, orders are not transferred, even if you have made a different setting for the Supply Chain Planning interface for SAP APO.

Further Information

For more information, see the SAP Libraray - SAP Advanced Planner and Optimizer, following this menu path: APO - Cross-Application Topics-> Subcontracting.