Ansicht
Dokumentation

/AFS/SIMGPP_PRSZVLDY - Define Validity Periods for Distribution Profiles

/AFS/SIMGPP_PRSZVLDY - Define Validity Periods for Distribution Profiles

SUBST_MERGE_LIST - merge external lists to one complete list with #if... logic for R3up   General Data in Customer Master  
This documentation is copyright by SAP AG.
SAP E-Book

You can create distribution profiles for the distribution of planned independent requirements. You can define them material-dependent or material-independent. During the presizing the distribution of the planned independent requirements is carried out according to this profile. For this you must enter a validity period. Beyond this period or if no distribution profile exists, the planned independent requirements are equally distributed.

Plant Validity period No. Date from Date to

0001 Christmas 1 01.11.2000 24.12.2000
0001 Christmas 2 01.11.2001 24.12.2001
0001 Christmas 3 01.11.2002 24.12.2002

To define different validity periods for distribution profiles, you have to maintain the following settings:

  • Plant
  • Validity period
  • Number of time interval
  • Date from
  • Date to

You can use one or several time intervals at client or plant level. If you define the distribution for a material or profile at plant level, the time intervals for several plants can differ.

Specify a plant for which a certain distribution is relevant within a certain period. For this enter a validity period and assign a number. Enter a time interval.

You can maintain distribution profiles at plant, category, grid value and/or period level. You can use the four profiles simultaneously.

In the view AFS Basic data of the material master you assign material-independent distribution profiles to a material at client level. In the view AFS MRP you maintain the assignment at plant level.