/CPD/V_RM_PICM - Mark Issues and Changes As Relevant for Risk Management

/CPD/V_RM_PICM - Mark Issues and Changes As Relevant for Risk Management

Addresses (Business Address Services)   Vendor Master (General Section)  
This documentation is copyright by SAP AG.
SAP E-Book

If you use Project Issue and Change Management,the system allows you to mark an issue or change request as relevant for risk management.

To mark the issue type General Issueas relevant for risk management, do the following:

  1. Go to Customizing for Commercial Project Management-> Project Issue and Change Management -> Processing of Issues, Change Requests, and Activities-> Processing of Issues and Change Requests-> Define Issue and Change Request Types.
  2. In the Issue Typeview, select the row corresponding to General Issue(issue type I1).
  3. Go to the Reference Objectsview.
  4. Choose New Entriesand enter RSK as the new object type.
  5. In the same row, under the dependent object access (DepObjAccess) column, enter issue reference (IR) as the corresponding value and save your changes.






CPI1466 during Backup   RFUMSV00 - Advance Return for Tax on Sales/Purchases  
This documentation is copyright by SAP AG.