The posting statuses for the "Multiple Control Principle" are to be set up in this activity.

The principle for multiple control needs to be activated in the Define RBD Area activity.

Three posting statuses are to be defined for RBD area 0001:

RBD Area Rel. Status Release Status (Text)
0001 10 In Quality Assurance
0001 20 In Release
0001 30 Released/Posted

Following the planned record update and subsequent processing of the planned record (using the ECF valuation sheet, for example), the processor can change the status of the planned record to status 10 "In Quality Assurance" by choosing the "Release OK" button @8X@. It is no longer possible to adjust data at this point. A processor with the relevant authorization (which can be set in the Definition of Status Change with Authorization activity) can also set the status of the planned record to status 20 "In Release" by choosing the release button. As soon as the final posting status 30 "Released/Posted" is set, the planned record is posted.