Upgrade 3.1i to 4.6c

Saplings:


I was wondering if it is a good idea to run SGEN or ABAP generation step
together with upgrade/hotpack. It takes forever to finish and just hold up
the whole process. Does anyone know a good way to generate all programs
after upgrade/hotpack? I try touchall, it still miss out some programs.

Zhihong Zhao
SAP Certified Basis Consultant
DairyFarmers - IS Department

-----Original Message-----
From: Matt Milne [mailto:matthewmilneZh...]
Sent: Wednesday, December 12, 2001 11:55 AM
To: DoNotReply@consolut.eu; Sap400 (E-mail)
Subject: Upgrade 3.1i to 4.6c


Just a quick note to the group with some metrics for a 3.1i to 4.6c upgrade
on a test v4r5 test machine. This was the first try and it worked with no
real problems. Scary .....

Prepare run time = 24 hours
R3UP run time = 4.5 days including the ICNV conversion and SGEN
activation. This include some down time overnight and a few hours SPDD/SPAU
Database before upgrade = 57G
after upgrade = 76.5G


Matt Milne



[Non-text portions of this message have been removed]


Durban Tours - Südafrika Safari

Vendor Master (General Section)   General Data in Customer Master  
This documentation is copyright by SAP AG.

Length: 1796 Date: 20240620 Time: 024042     sap01-206 ( 2 ms )