CY01_VERSION_CHANGE_BY_PRIO - Automatisches Umplanen anhand der Priorität der Versionen
CL_GUI_FRONTEND_SERVICES - Frontend Services CPI1466 during BackupDiese Dokumentation steht unter dem Copyright der SAP AG.
Funktionalität
If an operation belonging to a planned order cannot be dispatched because of whatever reason, while 'Cancel scheduling due to error' indicator in the strategy profile is set, this routine is called.
It checks if the current work center is the production line of a production version or if there is already a production version used in the planned order. If a production version can be found, the module search the next production version ('Next' in the sense of the table of valid versions sorted by the version ID).
If such a version can be found, the planned order is rescheduled with that new version.
Beispiel
Hinweise
Weiterführende Informationen
Parameter
AFVGD_IMPERROR_OUT
IN_AFVG_LINE
OPR_AFFECTED_OUT
PLAF_IMP
Ausnahmen
Funktionsgruppe
CY26SUBST_MERGE_LIST - merge external lists to one complete list with #if... logic for R3up RFUMSV00 - Advance Return for Tax on Sales/Purchases