Ansicht
Dokumentation

RAAUFW02 - Revaluation and New Valuation of Assets

RAAUFW02 - Revaluation and New Valuation of Assets

Fill RESBD Structure from EBP Component Structure   TXBHW - Original Tax Base Amount in Local Currency  
This documentation is copyright by SAP AG.
SAP E-Book

Purpose

Revaluation and/or New Valuation of Assets

Integration

Prerequisites

Features

Selection

The type of valuation selected (revaluation or new valuation) depends on the tab that was active at the time the report was started. If variants are used, the system automatically activates the appropriate tab.

Standard Variants

SAP ships a variant in which selection fields that are not required are hidden. This variant is the default starting variant. You can display the hidden selection fields if you want.

Output

The data is output in an ALV grid list. You can display additional fields there.

Notes

In file-based mass processing, you can use either a text file or an Excel file. The Excel file can only be edited by means of a workstation upload (this applies to both dialog mode and background mode). The upload reads a maximum of 5,000 lines. If the file is larger, it is truncated. You should therefore break up the file into smaller files if necessary.

Insert a line in the file for each asset to be edited. The line layout looks like this:

  • Company code
  • Asset main number
  • Asset subnumber
  • Value of asset after new valuation
  • Offsetting account for the posting (optional)
  • Evaluation group for master data update (optional)

Do not enter a header line!!!

A text file can be edited with a workstation upload or on the server. Use a comma as a separation character between the individual fields. Use a period as the decimal point. The line layout is the same.

Activities

Example






CPI1466 during Backup   RFUMSV00 - Advance Return for Tax on Sales/Purchases  
This documentation is copyright by SAP AG.

Length: 2023 Date: 20240520 Time: 135727     sap01-206 ( 35 ms )