/SEPC/PROJS_PROJ_READ_COSTS - PS Cost Data
SUBST_MERGE_LIST - merge external lists to one complete list with #if... logic for R3up CL_GUI_FRONTEND_SERVICES - Frontend ServicesThis documentation is copyright by SAP AG.
Functionality
This function module will provide both planned and actual costs for WBS Elements,
Activities, and Activity Elements related to a specific Project (in the
Project Systems module). Both planned and actual costs are summarized
by cost element and work or quantity Unit of Measure.
Input parameters:
IV_PROJECT_DEFINITION: An SAP project number
IV_LEDGER: The Ledger number that stures cost information for the project
IV_VERSION: The costing version
IV_PLAN: An 'X' in this field indicates that the function module should return
planned cost values
IV_ACTUAL: An 'X' in this field indicates that the function module should return
actual cost values
IV_COST_ELEM_GRP: The name of a cost element group. If a cost element
group is defined, the DATE and COAREA fields are also required. If
an entry is made in this field, the function module will determine a list of
Cost Elements included in the Cost Element Group. The function module will then
only display planned and actual costs for this specific group.
As an example, please assume that Cost Elements A, B, C, and D exist.
Cost Elemenets A and C are assigned to Cost Element Group X. Next,
assume an Activity Element has actual costs for cost elements A, B, C,
and D. If the user were to execute this function module and enter Cost Element
Group X as an input parameter, the results table (E_ACTUAL_COSTS) would
only show costs assigned to Cost Elements A and C.
IV_DATE: The validity date of the Cost Element Group Assignments. By
default, this is set to the system date.
IV_COAREA: The Controlling Area for Cost Element selection for the Cost
Element Group.
IV_NO_FISC_YEAR: Mark this field with an 'X' if you do not want the
fiscal year of the CO posting listed in the output tables (
ET_PLAN_COSTS and ET_ACTUAL_COSTS). This is useful to avoid multiple
rows in the output table for each cost element for each fiscal year
posting
IT_COSEL: This table allows the user of the function module to further limit
the planned or actual cost selection. This table works in a similar
fashion to an SAP selection option table. The user can define
additional limitations for planned or actual cost selections based on
the entries in this table.
As an example, please assume that Cost Elements A, B, C, and D exist.
Cost Elemenets A and C are assigned to Cost Element Group X. Next,
assume an Activity Element has actual costs for cost elements A, B, C,
and D. If the user were to execute this function module and enter Cost Element
Group X as an input parameter, the results table (ET_ACTUAL_COSTS) would
only show costs assigned to Cost Elements A and C. Assume the user
makes the following entry in table IT_COSEL:
Field = KSTAR
Sign = I
Option = EQ
LOW = B
KSTAR is the field name in the cost table for Cost Element. In essence,
we are telling the function module to also choose costs related to Cost Element B
(In addition to Cost Elements A and C which were chosen based on Cost
Element Group X). The results table (ET_ACTUAL_COSTS) would now show
costs assigned to Cost Elements A, B, and C.
!!Caution!! Entries table IT_COSEL can negatively impact the results
of the function module. Within the function module execution logic, IT_COSEL is filled with
various values based on the user import selection values. Please use
caution when utilizing this functionality!!
A list of values that can be used in the field FIELD in table IT_COSEL,
please use the ABAP Dictionary (SE11) and display either table COSS or
COSP.
Export TablesET_PLAN_COSTS: The planned costs assigned to the various cost objects
of the project.
ET_ACTUAL_COSTS: The actual costs assigned to the various cost objects
of the project.
The following is a description of each of the output columns in these
tables:
SOURCE_TYPE: Defines the cost object. Possible values are: WBS_ELEMENT,
ACTIVITY, or ACTIVITY_ELEMENT.
SOURCE: The cost object itself. If SOURCE_TYPE is WBS_ELEMENT then the
source field will contain the WBS Element. If SOURCE_TYPE is ACTIVITY
then the source field will contain the concatenated value of the network
- Activity. If SOURCE_TYPE is ACTIVITY_ELEMENT then the source field
will contain the concatenated value of the Network - Activity - Activity
Element.
OBJECT_NO: The internal SAP Object Number for the cost object.
FISC_YEAR: The fiscal year of the cost posting.
COST_ELEM: The Cost Element of the cost posting.
VALUE_TRANS_CUR: The costs for the cost object in transaction currency
TRANS_CUR: Currency Key for the transaction currency
VALUE_OBJECT_CUR: The costs for the cost object in object currency
OBJECT_CUR: Currency Key for the object currency
VALUE_COAREA_CUR: The costs for the cost object in Controlling Area
currency
OBJECT_CUR: Currency Key for the Controlling Area currency
QUANTITY: The planned or actual quantity (In the case of Labor, this
would be the planned or actual labor hours. In the case of components,
this would be the planned or actual component quantity).
QUANTITY_UNIT: The unit of measure of the Quantity field
ET_RETURN: This table provides messages generated from the function module
Example
Notes
Further information
Parameters
ET_ACTUAL_COSTSET_PLAN_COSTS
ET_RETURN
IT_COSEL
IV_ACTUAL
IV_COAREA
IV_COST_ELEM_GRP
IV_DATE
IV_LEDGER
IV_NO_FISC_YEAR
IV_PLAN
IV_PROJECT_DEFINITION
IV_VERSION
Exceptions
Function Group
C/SAPLPROJSBAL_S_LOG - Application Log: Log header data CPI1466 during Backup
This documentation is copyright by SAP AG.