BAPI_PDTRANSCO_POSTACTINPUT - Planning Data Transfer: Post Activity Input

BAPI_PDTRANSCO_POSTACTINPUT - Planning Data Transfer: Post Activity Input

BAL Application Log Documentation   PERFORM Short Reference  
This documentation is copyright by SAP AG.
SAP E-Book

Functionality

This method checks whether primary costs can be planned correctly.

Example

You want to plan primary costs in cost center 4210, cost center 4220, activity type 110, and business process 1004210.

On each occasion you plan using cost element 400000, - cost centers with $2400 fixed and $100 variable, (controlling area currency), the business process with just $3000 fixed.

To do so, you fill the tables as follows:

INDEXSTRUCTURE:

OBJECT_INDEX | VALUE_INDEX | ATTRIB_INDEX

1 | 1 | 0

2 | 1 | 0

3 | 2 | 0

The zeros indicate that no values were transferred. The system takes the planned values or the default values from the master data instead.

COOBJECT:

OBJECT_INDEX|COSTCENTER|ACTTYPE|ORDERID|WBS_ELEMENT|CO_BUSPROC

1 | 4210 | | | |

2 | 4220 | 110 | | |

3 | | | | | 1004210

TOTVALUE:

VALUE_INDEX|COST_ELEM|...|TRANS_CURR|...|FIX_VALUE|...|VAR_VALUE|DK|...

1 | 400000 | | | | 2400 | | 100 | |

2 | 400000 | | | | 3000 | | | |

DK is the relevant DIST_KEY_XXXX

TRANS_CURR does not need to be specified in this case. You only need to set the PLAN_CURRTYPE in the HEADERINFO to "C" (controlling area currency).

The system then checks the master records accordingly.





Parameters

COOBJECT
HEADERINFO
INDEXSTRUCTURE
PERVALUE
RETURN
TOTVALUE

Exceptions

Function Group

6031

CL_GUI_FRONTEND_SERVICES - Frontend Services   RFUMSV00 - Advance Return for Tax on Sales/Purchases  
This documentation is copyright by SAP AG.

Length: 2488 Date: 20240523 Time: 152133     sap01-206 ( 31 ms )