EXIT_SAPLCJG1_004 - PS Info System: Fill Nodes in Network/Hierarchy and Structure with Info
ROGBILLS - Synchronize billing plans rdisp/max_wprun_time - Maximum work process run timeThis documentation is copyright by SAP AG.
Functionality
This function module can only be used as an enhancement module. The customer can use it to enhance the node information in the legends of the network graphic, the hierarchy graphic, and the structure graphic in the information system. This means that new information can be displayed in new fields or in the existing fields of the corresponding nodes. Normally the legend is only supplied with data in this way, when the user displays user-specific information in the nodes of the the network graphic, the hierarchy graphic, or the structure graphic in the information system.
The text index forms the link between the node type in Customizing and the actual node in the graphic. It is contained in every field of a format. The node text is transferred in the node attributes to the graphic.
In the standard system the following text indices are already used. They can be overwritten.
Call from the network graphic
- NET_CONST-TEXT_INDEX_0 (= 0) -> Activity number
- NET_CONST-TEXT_INDEX_1 (= 1) -> Control key
- NET_CONST-TEXT_INDEX_3 (= 3) -> Activity short text
- NET_CONST-TEXT_INDEX_10 (= 10) -> Object number
Depending on the set of dates the following text indices are used:
- NET_CONST-TEXT_INDEX_2 (= 2) -> Duration
- NET_CONST-TEXT_INDEX_4 (= 4) -> Earliest scheduled start
- NET_CONST-TEXT_INDEX_5 (= 5) -> Latest scheduled start
- NET_CONST-TEXT_INDEX_6 (= 6) -> Free float
- NET_CONST-TEXT_INDEX_7 (= 7) -> Total float
- NET_CONST-TEXT_INDEX_8 (= 8) -> Earliest scheduled finish
- NET_CONST-TEXT_INDEX_9 (= 9) -> Latest scheduled finish
If the graphic is called up for plant maintenance the following fields are also used:
- NET_CONST-TEXT_INDEX_26 (= 26) -> Earliest start time
- NET_CONST-TEXT_INDEX_27 (= 27) -> Latest start time
- NET_CONST-TEXT_INDEX_28 (= 28) -> Earliest finish time
- NET_CONST-TEXT_INDEX_29 (= 29) -> Latest finish time
Call from the hierarchy graphic
- NET_CONST-TEXT_INDEX_0 (= 0) -> WBS element number
- NET_CONST-TEXT_INDEX_1 (= 1) -> WBS element short text
- NET_CONST-TEXT_INDEX_2 (= 2) -> WBS element basic start date
- NET_CONST-TEXT_INDEX_3 (= 3) -> WBS element basic finish date
- NET_CONST-TEXT_INDEX_4 (= 4) -> WBS element forecast start date
- NET_CONST-TEXT_INDEX_5 (= 5) -> WBS element forecast finish date
- NET_CONST-TEXT_INDEX_6 (= 6) -> WBS element actual start date
- NET_CONST-TEXT_INDEX_7 (= 7) -> WBS element actual finish date
Call from the structure graphic
- NET_CONST-TEXT_INDEX_0 (= 0) -> Object type
- NET_CONST-TEXT_INDEX_1 (= 1) -> Object ID
- NET_CONST-TEXT_INDEX_2 (= 2) -> Short text
Example
If you want the short text that appears in the 1st field toidepend on the field "ACTIVITY_IMP" ,insert following coding into the include of this function module:
LIF ACTIVITY_IMP IS INITIAL.
NVALS_TAB_IMP-ID,,=,,LEGEND_ID_IMP.
NVALS_TAB_IMP-FL,,=,,NET_CONST-TEXT_INDEX_1.
NVALS_TAB_IMP-VAL,,= ,,' WBS element short text'.
APPEND NVALS_TAB_IMP.
ELSE.
NVALS_TAB_IMP-ID ,,=,,LEGEND_ID_IMP.
NVALS_TAB_IMP-FL ,,=,,NET_CONST-TEXT_INDEX_1.
NVALS_TAB_IMP-VAL,,= ,,' Activity short text'.
APPEND NVALS_TAB_IMP.
Notes
The "ACTIVITY_IMP" indicator specifies whether the legend node is an activity node. If the indiator is initial, it is a WBS element node.
Parameters
ACTIVITY_IMPLEGEND_ID_IMP
NVALS_IMP
Exceptions
Function Group
XCN1Fill RESBD Structure from EBP Component Structure General Material Data
This documentation is copyright by SAP AG.