New Variants of Maintenance Plans ( RELNPM_40A_PRM_010_STRAT )

New Variants of Maintenance Plans ( RELNPM_40A_PRM_010_STRAT )

PERFORM Short Reference   RFUMSV00 - Advance Return for Tax on Sales/Purchases  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

New Variants of Maintenance Plans

Description

With Release 4.0A, the control of planned maintenance has been made more flexible. The following variants of maintenance plans are available:

  • Strategy-based maintenance plans
The maintenance strategy defines the number and frequency of the packages.
  • Multiple counter maintenance plans
The assigned counter/time defines the due date for the next call.
  • Single cycle plan (new for 4.0A)
You can now define a maintenance cycle directly in the maintenance plan. This maintenance plan corresponds to a strategy-based maintenance plan with exactly one time-based or counter-based package. In this case, you no longer have to create a strategy and you also do not have to perform the assignment of operations for exactly this one package. The total work contents of the task list entered are called up each time.

Damage caused to data by errors

Software/hardware requirements

Installation information

Effects on System Administration

For the different maintenance plan variants, there are three new transactions for creating maintenance plans, for which only the relevant entries are necessary:

  • Create single cycle plan
  • Create strategy-based maintenance plan
  • Create multiple counter plan

Effects on Customizing

Effect on batch input

Changes to the Interface

Changes in procedure

Procedure for removing dataset errors

Dependent functions

Planning

Further notes