Change Status of Task Lists and Scheduling (Changed)

Use

From SAP R/3 Enterprise Core 4.70 (SAP_APPL 470) the validity date of the task lists (particularly the assignment of maintenance packages at operation level) is considered correctly during the scheduling of maintenance plans.

Task lists are connected with engineering change management. You can use engineering change management to change the master data of the task list with date validity. This can mean that data which is valid today is no longer valid in the future because the data has been changed, deleted or amended. Among this task list data are the maintenance packages to which individual operations can be assigned.

The maintenance packages are, in turn, the basis for scheduling strategy-based maintenanceplans.

The scheduling determines a "first" scheduling screen for this totality of "used" packages. If a schedule is determined with a concrete plan date, then the system checks the validity of the packages for this date. Invalid packages are deleted and not displayed. If there is no valid package for the determined date, then the whole schedule is deleted. Subsequent schedules are based on this schedule and continue the package sequence of the strategy.

Displaying the task list in the maintenance plan

The cycles (packages) current used are displayed in the master data of a strategy plan or a maintenance item with strategy reference. In the maintenance plan header or in the maintenance item, the display can take place at a freely definable time. The system determines the respective status for valid cycles and displays these.

Adaption of maintenance plan costing

The maintenance plan costing uses the calls that exist in a costing period for a maintenance plan (as well as calls with the status called up and also waiting). The dates that are still outstanding in this period are "simulated" on the basis of the existing dates. This simulation for strategy plans takes place under consideration of engineering change management for task lists.

Adaption of graphic scheduling overview

In the graphic scheduling overview you can simulate additional schedules for a freely definable period of time in addition to the pre-existing schedules. The simulation for strategy plans also takes place under consideration of engineering change management for task lists.

Effects on Existing Data

Effects on Data Transfer

Effects on System Administration

Effects on Customizing

Further Information






ABAP Short Reference   TXBHW - Original Tax Base Amount in Local Currency  
This documentation is copyright by SAP AG.

Length: 3437 Date: 20240523 Time: 061244     sap01-206 ( 80 ms )