Fiscal Year Planning (new) ( RELNPPM_50_PFM_FISC_YEAR )

Fiscal Year Planning (new) ( RELNPPM_50_PFM_FISC_YEAR )

Fill RESBD Structure from EBP Component Structure   General Material Data  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

Fiscal Year Planning (new)

Use

As of SAP Portfolio and Project Management 5.0, you can define and display data in fiscal year format and therefore use the fiscal year variant for planning a fiscal year in SAP Portfolio and Project Management.

Financial Period Breakdown

For financial and capacity planning, a specific period breakdown according to the fiscal year definition is supported.

Year to Date Values

If you have activated the fiscal year planning, the year-to-date values represent the values from the first periods (P1) of the current fiscal year until the current period.

Exchange Rates

If you have activated the fiscal year planning, the system uses one exchange rate per period during the import from SAP ERP. To determine the exchange rate, the system uses the first day of the period.

Effects on Existing Data

Effects on Data Transfer

In case financial values are being imported from the SAP ERP system by linking a portfolio item to a PS project element, the fiscal year variant used for the PS project element and the portfolio item must be the same.

If you use several Controlling areas, for example if you have connected several SAP ERP systems, then you only can import into the portfolio if the fiscal year variants of the Controlling areas are the same.

Effects on System Administration

Migration Reports

If you have switched on 0010 Portfolio Item FI/CO Planning and Integration -> 0006 Fiscal Year Switch (see SAP Note 1457426), you must use the /RPM/MIGRATION_CAL_TO_FISCAL report to transfer the values from calendar year format to fiscal year format.

If you want to copy the fiscal year variants from the SAP ERP system, you can use the /RPM/FISCAL_VARIANT_COPY report.

Effects on Customizing

  • To use fiscal year planning, you must have switched on the following:
  1. 0002 Master Switch -> 0008 Enhanced Capital and Resource Mgmt Switch (see SAP Note 1457426) in Customizing for SAP Portfolio and Project Management under Portfolio Management -> Global Customizing -> Global Settings -> Override Default Global Settings. For more information, see Capital and Resource Management (enhanced).
  2. 0010 Portfolio Item FI/CO Planning and Integration -> 0006 Fiscal Year Switch (see SAP Note 1457426) in Customizing for SAP Portfolio and Project Managementunder Portfolio Management -> Global Customizing -> Global Settings -> Override Default Global Settings.
  3. If you would like to use a default fiscal year variant for processing, you must have set the value 0010 Portfolio Item FI/CO Planning and Integration -> 0007 Default Fiscal year variant (see SAP Note 1457426) in Customizing for SAP Portfolio and Project Management under Portfolio Management-> Global Customizing -> Global Settings -> Override Default Global Settings.
  • You defined fiscal year variants in Customizing for SAP Portfolio and Project Management under Portfolio Management-> Global Customizing -> Global Settings -> Maintain Fiscal Year Variant.
  • You defined the used fiscal year variant on the portfolio level in Customizing for SAP Portfolio and Project Managementunder Portfolio Management -> Global Customizing -> Portfolio-Dependent Settings -> Define Portfolio Types.

Further Information

Release Note: Capital and Resource Management (Enhanced).






BAL Application Log Documentation   General Material Data  