Changed Quantity Calculation for Milestone and Progress Confirmations

Use

You can set up milestone and progress confirmations so that the quantities (yield and scrap) of automatically generated confirmations are calculated without taking into account the planned scrap percentage rate of each operation. The automatic confirmations are then posted with the same total quantity as the milestone or progress confirmation. Scrap is posted as yield in the automatically generated confirmations.

If you do not select this procedure, the planned scrap percentage rate of each operation is taken into account when calculating the confirmed quantity. In the generated confirmations, the proportional scrap is displayed separately.

Procedure prior to 4.6C

Prior to Release 4.6C, there was only a procedure for automatically generated confirmations. Scrap was posted as yield in the automatically generated confirmations. The confirmed total quantity was calculated proportionally from the planned operation quantities (yield and scrap).

Effects on Customizing

You make this setting in the confirmation parameters (tab page Generally valid settings, "Generated confirmations w/o quantity adjustment" indicator).

Customizing for Shop Floor Control: Operations -> Confirmation -> Define Confirmation Parameters.

Further Information

For more information and an example, refer to the documentation for the Generated confirmations w/o quantity adjustment indicator.