MRP: Planning for Components to be Provided in Subcontracting ( RELNPP_MRP_40A_BEISTELLK )

MRP: Planning for Components to be Provided in Subcontracting ( RELNPP_MRP_40A_BEISTELLK )

RFUMSV00 - Advance Return for Tax on Sales/Purchases   General Data in Customer Master  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

MRP: Planning for Components to be Provided in Subcontracting

Description

As of release 4.0, the net requirements calculation for the components to be provided in subcontracting takes into consideration that the stock of material provided to the subcontractor can only be used to cover the appropriate requirements for material provided. Therefore, the component stock (stock provided) already provided to the vendor (subcontractor) can only be used to cover the requirements for material provided to this particular subcontractor.

The system only uses the stock of material provided that has not been assigned to a subcontractor as unrestricted-use stock to cover all requirements.

Damage caused to data by errors

Software/hardware requirements

Installation information

Effects on System Administration

Effects on Customizing

Effect on batch input

Changes to the Interface

Subcontracting Planning Segment:

In an additional planning segment for subcontracting, the system displays the stock and requirements for material provided in the MRP list and the stock/requirements list. A separate planning segment is created for each vendor (subcontractor) for which stocks or requirements for material provided exist. The system displays stock/requirements for material provided for information purposes only. Actual planning occurs in the net requirements segment.

Planning in the Net Requirements Segment:

In the net segment, the system calculates the difference between stock already provided and requirements for material provided.

The system does not include requirements that are covered by existing stocks at the subcontractor's plant for material provided to a subcontractor in the net requirements calculation. The system also does not display the requirements.

The system displays and plans requirements for material provided to a subcontractor that are not covered by stocks already provided.

Changes in procedure

Procedure for removing dataset errors

Dependent functions

Planning

Further notes






BAL_S_LOG - Application Log: Log header data   ROGBILLS - Synchronize billing plans  
This documentation is copyright by SAP AG.

Length: 2493 Date: 20240604 Time: 001043     sap01-206 ( 62 ms )