Planning Run: Creating Total Records for Dependent Requirements
Description
You can greatly increase the performance of the MRP run for products with a high number of components by creating total dependent requirements for the components.
The system does not create individual records per pegged requirement in table RESB for components for which it is possible to create total dependent requirements when using this total dependent requirements process. Instead, the system creates a totals record per component in table RQID that contains the cumulative quantity of all requirements per component.
Table (RQHD) contains the header information for the BOM explosion and controls how the system creates total dependent requirements.
Prerequisites
The material or component must meet the following conditions to carry out this process:
- Finished product:
- The material must be allowed for repetitive manufacturing and have a repetitive manufacturing profile that allows the creation of total dependent requirements.
- Components:
- The system can only create total dependent requirements for those components that are not produced using make-to-order production. You must therefore set the individual/collective indicator for the components accordingly in the material master record.
Example
You have 1000 components for a finished product and an order volume of 1000 per day.
The system
writes a total dependent requirements record for each order without total dependent requirements which results in a total of 1,000,000 records.
If, however, the system can create total dependent requirements records for all 1000 components, the
system creates only one totals record per component. That means, the number of records can be reduced to 1000.
If you carry out an availability check for 200 of the 1000 components, the system creates individual records and totals records for these components.
This amounts to 200,000 individual records and 200 totals records. The system creates only totals records for the remaining 800 components, which amounts to 800 records.
In this example the number of records is reduced from 1,000,000 to 201,000 records.
Damage caused to data by errors
Software/hardware requirements
Installation information
Effects on System Administration
Effects on Customizing
You can make the settings for the repetitive manufacturing profile in Customizing for Repetitive Manufacturing. For more information on this topic, read the IMG for the next chapter:
Specify control data for repetitive manufacturing profiles
Effect on batch input
Changes to the Interface
Changes in procedure
The system displays the total dependent requirements as total requirements in the evaluations of MRP. It is not possible to view pegged requirements for the total requirements.
In the planned order you can view the components for which the system created the total dependent requirements via a special list. In the standard component list, the system only includes those components for which individual records were created.
Procedure for removing dataset errors
Dependent functions
Planning
Further notes
In the following instances, the system creates an individual dependent requirement record in addition to a total dependent requirement record:
- If you allow the availability check for the material in the material master record
- If you define in the material master record that the system is to also create individual records by using the Requirements grouping indicator
Addresses (Business Address Services) BAL Application Log Documentation
This documentation is copyright by SAP AG.
Length: 4285 Date: 20240523 Time: 065331 sap01-206 ( 73 ms )