Evaluation Lists: End of the Total Replenishment Lead Time Displayable ( RELNPP_MRP_46A_GESAMT )

Evaluation Lists: End of the Total Replenishment Lead Time Displayable ( RELNPP_MRP_46A_GESAMT )

Fill RESBD Structure from EBP Component Structure   ABAP Short Reference  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

Evaluation Lists: End of the Total Replenishment Lead Time Displayable

Scope of Functions

The total replenishment lead time for all levels of production is the time in which the replenishment of materials is critical. This is why many users in the MRP list or the stock/requirements list are primarily interested in the planning situation before the end of the total replenishment lead time.

By using a pushbutton, you can display the end of the total replenishment lead time in these lists in its own row. You can activate this setting either just for the current display or save it as a user-specific default value.

The display of the total replenishment lead time is only for information purposes; it does not affect MRP.