Materials in Projects: Changes in Release 3.0

Description

The following changes were made in Release 3.0:

  • Projects can have their own stock (project stock) as seen from an MRP point of view.
You can define whether individual stock management is allowed using the Project stock indicator in the project profile and defined for each project definition via the Details -> Profile data menu.
Ob ein Projekt eine Einzelbestandsführung zuläßt, kann über das
In addition, the material that is to be part of project stock must be assigned in the material master to a MRP group which allows project stock.
  • You can use the Reservation/PReq. indicator in the network to determine that no purchase requisitions are created and that no reservations are relevant for MRP.
You can also use this indicator to prevent the project from being executed while still in the quotation stage.
Planned costs for purchase requisitions and reservations are still calculated and updated.
Reservations and purchase requisitions can be activated:
  • for individual activities

  • for one network

  • for one WBS element

You enter the indicator as a default value in the network profile so it is copied into the header when you create a network. The indicator is copied automatically into all activities and activity elements that you create.
  • From the component overview, when you select Components -> Explode BOM, you can breakdown a single-level BOM and alloate the material components to network activities.

When you allocate materials to activities, you can select from the various account assignment categories for purchase requisitions listed here:

  • In the network you can reserve stock components for project stock, sales order stock or for plant stock.
The component inventory quantities are managed by the respective stock.
  • You can create purchase requisitions for non-stock items which lead to preliminary orders for the WBS element or sales order.
  • You can also create purchase requisitions for non-stock items which convert into a third-party order for the WBS element. You can maintain the third-party order address via Components -> Maintain address.
  • You can also create purchase requisitions for non-stock items and sales orders for WBS element.
  • Furthermore, you can also create a purchase requisition for non-stock items whose planned costs are updated to the network.
  • Reservations and purchase requisitions for stock and non-stock items (sales order stock) for a sales document such as a sales order, which are settled to a project are handled as follows:
The values are updated to the same WBS element where the sales document is settled.
The quantities are updated to the sales document.

Commitments for purchase requisitions and planned costs for reservations are determined as follows:

  • When you create reservations and purchase requisitions for sales order stock or project stock, planned costs will not be updated in the WBS elements.
  • When you create reservations and purchase requisitions for plant stock, the planned costs will be updated in the network.
  • When you create purchase requisitions, the system determines the commitment values and updates the WBS elements, network, or sales order.

Effects on Customizing

  1. If necessary, maintain the Reservation/PReq. indicator in the network profile: Additional information
  2. If necessary, maintain the Project stock indicator in the project profile: Additional information
  3. If necessary, define a release strategy in the Implementation Guide of Purchasing with which you can create a request for quotation from a purchase requisition: Additional information
  4. If you want to use different account assignment types for purchase requisition and reservation, you must assign them to different purchasing account assignment categories in Customizing: Additional information

Further notes

Please refer to the Project System document for more information on the new functions and on changes for the material assignment in the network.