Work Breakdown Structure: Changes in Release 3.0

Description

In Release 3.0, the following changes were made in the work breakdown structure (WBS):

  • You can create documents directly while in WBS maintenance and assign them to individual WBS elements.
  • You can create new work breakdown structures by copying a standard WBS.
  • You can lock project coding for (standard) WBS in Customizing to prevent other projects from being created with the same coding.
  • You can enter a special character for project editing in Customizing that allows you to quickly create WBS elements. The system always copies the ID of the superior WBS element or the project definition.
Example: In Customizing, you have defined the character " as a possible entry (F4). In the work breakdown structure, when you insert a new WBS element under the WBS element A-123-LDZ-10, you only have to enter "20".
The system copies the ID from the superior WBS element as follows: A-123-LDZ-.
  • WBS element currency
WBS elements can have their own object currency. The currency in the project definition is only a default currency for new WBS elements. You can change the WBS element currency as long as no currency-dependent rates (cost planning, actual, and so on) exist.
  • You can use subprojects for fixed price agreements between WBS elements.
The WBS can be split up into individual subprojects. Subprojects consist of hierarchically related WBS elements and are called a "subtree" of the entire work breakdown structure.
Each subproject is identified by a unique name. There cannot be two subprojects with same name for one project definition, however, you can use a subproject name for different project definitions.
You enter the subproject name in the WBS element. If you subsequently break this WBS element down further, this identifier is passed on.

New fields

  • Use the project stock indicator to specify that the project has stock separate from normal stock for material requirements planning (MRP) purposes. Please refer to release note "Materials in the Projects" for more information on project stock.
  • You can specify which WBS elements are automatically classified when you create them.
With the change documents indicator, you specify that change documents are created for all master data in the work breakdown structure if status management allows the business transaction "Create change documents".
This business transaction is possible after the system status "release" has been set.
  • The following fields were included in time scheduling: Overall profile for the capacity planning table in both table and graphic form, profile for the project planning board, and profile for time scheduling.
  • The following fields were included for accounting: Financial budget profile, investment profile, interest profile, CO area, statistical indicator.

The following fields are defaults for the entire work breakdown structure:

  • Project stock indicator

  • Profile for WBS scheduling

The following fields are defaults for new WBS elements:

  • CO area

  • Statistical indicator

  • Jurisdiction code

  • Interest profile

  • Capital investment profile

  • Statistical indicator
  • Jurisdiction code
  • CO area
  • Interest profile
  • Capital investment profile
  • Weighting of percentage of completion
  • Change number
  • Subproject

Changes and new functions in the menus

The menu in the work breakdown structure was revised. All the menu options under the path Additional functions - > Details were moved out from menu Additional functions and introduced as a separate menu option Details. In the English version, the menu option Additional functionswas renamed Extras.

  • Using Copy from..., you can include standard WBS elements and standard projects.
  • The menu option Functions was renamed Status. In the Status menu, you set all statuses for the WBS.
  • The menu option Display/Suppress was renamed Expand/Collapse.
  • You can display and create versions via Project version.
  • Using Dates, you can display basic dates, forecast dates and actual dates for the WBS element.
  • In Milestone overview, you can maintain milestones.
  • You can now call up settlement rules for the WBS elements from this menu.
  • Using Earned value analys., you can maintain data for earned value analysis.
  • Using Create document, you can create documents for the WBS element.
  • Asset under constr. is used for capital investment.

Changes in the hierarchy graphic

  • Collapsed nodes (hidden WBS elements) are now represented as "stacked nodes".
  • The sequence of the WBS elements within a level, that is, with a common superior WBS element, can be changed any way you like: Just click the right mouse button to move them.
  • Title bar was added (for printing).

Effects on Customizing

New fields were included in Customizing for the project profile and the screens to be maintained were revised:

  • Basic data

  • Time scheduling

  • Accounting

  • Organizational data

If necessary, revise your project profile settings. Additional information.

Effect on batch input

As of Release 3.0, another screen is used for creating new WBS elements in the overview.

  • Up to and including Release 2.2: Screen 0301, field PRPS-POSID

  • As of Release 3.0: Screen 0300, field RCWBS-IDENT

Further notes

Please refer to the Project System document for more information on the new functions and the changes to the work breakdown structure.