Calculating the Planned Payment Flow in Projects ( RELNPS_40A_PLANFINANZ )

Calculating the Planned Payment Flow in Projects ( RELNPS_40A_PLANFINANZ )

BAL_S_LOG - Application Log: Log header data   BAL_S_LOG - Application Log: Log header data  
This documentation is copyright by SAP AG.
SAP E-Book

Short text

Calculating the Planned Payment Flow in Projects

Description

From Release 4.0, the planned payment flow for a project can be derived automatically from detailed project planning.

Planned down payments and down payment clearings are recorded under the new value type 6A; planned payments continue to be recorded under value type 62. Planned payments calculated automatically can be updated by day.

Debit-Side Planned Payment Flow

You can enter a billing plan for a billing element in your WBS. The system then generates planned payments in the WBS element automatically.

The data is recorded under commercial transaction PSFP.

Credit-Side Planned Payment Flow

The planned payment flow is derived from the planned data for activity-assigned networks. Choose Project management -> Planning -> Finances -> Network costing. For detailed planning, you can maintain planned outgoing payments in an activity-assigned network using an invoicing plan. The following data is included in the calculation:

  • Externally processed activity
  • Currency key and currency translation rate for the activity

  • End date with the latest dates or invoicing plan dates

  • Amount from activity or invoicing plan date

  • Terms of payment from the customer master or invoicing plan date

  • General costs activity
Specifications from the invoicing plan for the activity
  • Externally procured material component
  • Currency key and currency translation rate for the activity

  • Requirement date or invoicing plan dates

  • Amount from the component or from the invoicing plan date

  • Terms of payment from the customer master or invoicing plan date

The data is recorded under the commercial transaction KPPP. Calculation of credit-side plan payments is not supported for WBS elements or activity-assigned networks.

Prerequisites

  • You must activate Project Cash Management in the Implementation Guide.
Activate Project Cash Management in Company Code
  • Commercial transaction FIFA must be assigned to a number range group Maintain number ranges and a suitable number range must be created.

Damage caused to data by errors

Software/hardware requirements

Installation information

Effects on System Administration

Effects on Customizing

Effect on batch input

Changes to the Interface

To access the network costing for the credit-side planned financial data, go the Planning menu and choose Finances -> Network costing auf.

Changes in procedure

Procedure for removing dataset errors

Dependent functions

Planning

Further notes

Planned payments from billing plans in the WBS and from sales documents are not offset, but are added on. To change this, execute the step Financial budget update from sales order. in the Project System Implementation Guide.