Changes to Scheduling in the Project System ( RELNPS_46A_DAT )
BAL_S_LOG - Application Log: Log header data BAL_S_LOG - Application Log: Log header dataThis documentation is copyright by SAP AG.
Short text
Changes to Scheduling in the Project System
Scope of Functions
The WBS scheduling function has changed in Release 4.6A. You can now choose from the following preconfigured settings:
- Top-down scenario
- The dates for schedulign are prescribed by the project definition or WBS elements. The dates in the activities must be inside the range of the basic dates for the WBS element to which they are assigned.
- Bottom-up scenario
- The dates of the activities are passed up through the project structure from the activities to the WBS elements and from there to the project definition.
- Freely definable scheduling
- As before, you can configure the scheduling parameters as you want.
Other Changes
As has always been the case for activities, you can now show the earliest and latest dates in WBS elements separately in the graphic.
In addition, you can have the last scheduling run made or saved displayed as a shadow object in the graphic area.