Changes to the Structure of the Project System IMG ( RELNPS_46B_IMG )
PERFORM Short Reference Vendor Master (General Section)This documentation is copyright by SAP AG.
Short text
Changes to the Structure of the Project System IMG
Scope of Functions
The following nodes have been deleted:
- Under Costs>Planned costs>Manual cost planning in WBS> PSP>Detailed planning>Resources planning
- Pricing strategy
- Maintain resource prices
The following IMG nodes are new:
- Under Revenues and Earnings>Automatic and Periodic Allocations:
- Results Analysis>User-Define Error Management, with the activities:
- Specify User-Defined Message Types for WIP and Results Analysis
- Assign Messages to a Responsibility Areas
- Under
einem Verantwortungsbereich zuordnen
- Unter Information System>Costs/Revenues Information System> Hierarchy Report:
- Currency Translation, with the activity
- Define Currency Translation Keys
The following IMG nodes have been renamed:
- Under Structures>Operative Structures>Network:
- "Rename Variants" has become "Generate Change Profiles"
Effects on Existing Data
Effects on Data Transfer
Effects on System Administration
Effects on Customizing
Further Information
rdisp/max_wprun_time - Maximum work process run time CPI1466 during Backup