Changes to the Structure of the Project System IMG
Use
New Entries:
- New components:
- Claim
- Collaboration
- New grouping nodes with activities:
- Document Search in Web (under: Documents)
- Easy Cost Planning and Execution Services (under: Costs > Planned Costs)
- New individual activities
- Order Change Business Addin (under: Structures > Network > Enhancements for Networks)
- Evaluation in Info System (under: Progress Analysis)
- Define Scheduling Scenarios (under: Material -> Monitoring Dates)
Restructured Entries
- The new activity Create and Assign Commitement Items (under Payments > Commitment Items) replaces:
- The node Generate Commitment Items Automatically and the activities subordinate to it
- The node Create Commitment Items Manually and the activity Assign Single G/L Account to a Commitment Item
- The activity Maintain Progress Version (SIMG_OLPR_EWS) is replaced with a new activity SIMG_OLPR_VERSION_P) of the same name.
Deleted Entries
- The activity Define Profile for Progress Analysis Overviews (under: Information System > Technical Project Reports)
Effects on Existing Data
Effects on Data Transfer
Effects on System Administration
Effects on Customizing