OPS_PS_CI_1: Progress Tracking (Enhanced) ( RELNPS_603_OPSPS1_BS4 )
Vendor Master (General Section) BAL_S_LOG - Application Log: Log header dataThis documentation is copyright by SAP AG.
Short text
OPS_PS_CI_1: Progress Tracking (Enhanced)
Use
As of SAP ECC 6.0, Enhancement Package 3 (EA-APPL 603), business function Project System(OPS_PS_CI_1), Progress Tracking is also available for the following PS objects:
- Network activities
- Work breakdown structure (WBS) elements
Progress Tracking allows you to track the progress of work breakdown structure elements and network activities according to date information, priorities, and status of assigned events. The data can be entered manually, or derived from existing system data.
Effects on Existing Data
Effects on Data Transfer
Effects on System Administration
Effects on Customizing
To use this function, you must carry out the IMG activities under the structure nodes Settings for Work Breakdown Structures and Settings for Networks. Choose Project System -> Progress -> Progress Tracking
Further Information