SNP Priority Profile (New) ( RELNSCM410_APO_SNP_PRIO )
RFUMSV00 - Advance Return for Tax on Sales/Purchases CPI1466 during BackupThis documentation is copyright by SAP AG.
Short text
SNP Priority Profile (New)
Use
Previously, the product and resource decomposition solution methods were available for optimization in Supply Network Planning (SNP). Decomposition methods enable you to reduce runtime and memory requirements.
For product and resource decomposition, the system combines both products and resources in partial problems. These are then solved sequentially. Previously, the order in which the objects are combined and planned was determined automatically by the system.
As of SAP SCM 4.1, you can determine this order yourself by assigning priorities to the products and resources in an SNP priority profile. In this way, you can specify that important products and resources are planned first, for instance.
Effects on Existing Data
Effects on Data Transfer
Effects on System Administration
Effects on Customizing
You create the SNP priority profile in the current settings in SNP under Profiles -> Define Priority Profiles and assign it to an SNP or deployment optimizer profile in Customizing or in the current settings of SNP under Profiles -> Defined SNP Optimizer Profile or Define Deployment Optimizer Profile (on the Solution Methods tab page). If you do not define an SNP priority profile, the optimizer determines the sequence of objects as before.
Further Information
BAL_S_LOG - Application Log: Log header data BAL_S_LOG - Application Log: Log header data