Explanation Function and Results Indicators in Capable-to-Match (New)
Use
As of SAP SCM 5.0, you can see an explanation in the application logs after a CTM planning run as to why CTM did not cover or only partially covered demands. An explanation function with an explanation profile is available for this.
You activate the explanation function in the CTM profile on the Settings -> Technical Settingstab page, under Logs -> Generate Planning Explanation, by setting the Use Planning Explanation indicator and then specifying an explanation profile.
In addition, you can see the following results indicators in the log:
- Demand fulfillment per location product and demand type
- Sources of supply used per location product
- Resource utilization
The system calculates the results indicators at the level of the supply chain model used.
You activate the results function in the CTM profile on the Settings -> Technical Settingstab page, under Logs -> Generate Results Indicator, by selecting desired the results indicator.
You can transfer the results indicator for demand fulfillment with the DataSource ()APO_SDM_INDC_DEMSAT to SAP NetWeaver 2004s Usage Type Business Intelligence.
Effects on Existing Data
Effects on Data Transfer
Effects on System Administration
Effects on Customizing
Further Information