/CPD/ANLY_PROGANYVN - Set Up Progress Analysis Versions in Analytics

/CPD/ANLY_PROGANYVN - Set Up Progress Analysis Versions in Analytics

ROGBILLS - Synchronize billing plans   Fill RESBD Structure from EBP Component Structure  
This documentation is copyright by SAP AG.
SAP E-Book

In this Customizing activity, you define the progress version that must be used by the system to report project progress, in the Cross-Project View and for progress reporting in the Overview page of a commercial (master) project.

By default, the SAP standard solution ships 100as the value of the progress version. If you maintain multiple progress versions, only the first entry is considered.