CO_MES_INT_LOGSYS - Maintain Logical System for Distribution of Production Orders
ABAP Short Reference rdisp/max_wprun_time - Maximum work process run timeThis documentation is copyright by SAP AG.
In this Customizing activity, you activate the integration of production orders with a Manufacturing Execution System. You define how the logical system to which the production order is automatically distributed upon release is found.
Note: If you activate the business function LOG_PP_MES_INT_02 in your system, you can alternatively distribute production orders to an MES using the data replication framework (DRF).
You have made the ALE settings for the production optimization interface (POI). You will find these in the menu Logistics General --> Supply Chain Planning Interfaces (SCPI) --> Production Optimization Interface (POI) --> ALE Settings for POI.
Specify how the logical system for the distribution is to be found for a certain combination of plant and order type. You can use the placeholder (wildcard) '*' if the setting is to apply to all plants or order types.
- If you want to make the logical system dependent only upon the given parameters plant and order type of the production order, choose the determination method "Customizing Defines Logical System". Enter the logical system directly.
- If you need flexible control for the distribution of the production order, choose the determination method "BAdI Determines Logical System". The system then expects an implementation of the BAdI CO_MES_INT_DISTRIBUTION to determine the logical system from the order data.
- If you want to use the data replication framework for flexible determination of the logical system, choose the appropriate determination method. You must then maintain a distribution model for integration with the MES and specify filter criteria. For more information, see Basic Settings for MES Integration.
You want to distribute all production orders created in plant 0001 to the logical system ABC. Then maintain the following entry:
Plant | Order type | Determination method | Log. system |
---|---|---|---|
0001 | * | Customizing | ABC |
If you have maintained several entries with placeholders (wildcards), the system always uses the entry that is specified most precisely. The specification of the plant takes priority over specification of the order type, as shown in the following example:
Plant | Order type | Determination method | Log. system |
---|---|---|---|
0001 | * | Customizing | ABC |
* | PP01 | Customizing | XYZ |
* | * | BAdI |
All production orders created in plant 0001 are distributed to the logical system ABC in accordance with these settings, including those with the order type PP01. Production orders in other plants are distributed to the system XYZ if they have the order type PP01. The BAdI for determination of the logical system is invoked for production orders that were neither created in plant 0001 nor have the order type PP01.