CPRO_MSP_FIELDS - Assign Fields for Export from Project Management

CPRO_MSP_FIELDS - Assign Fields for Export from Project Management

rdisp/max_wprun_time - Maximum work process run time   Addresses (Business Address Services)  
This documentation is copyright by SAP AG.
SAP E-Book

In this Customizing activity, you map Project Management fields to base project system fields. This defines which fields are transferred from Project Management and how they should be transferred. You can also group object into main objects and subobjects.

The main object determines which Project Management data is transferred to the base system.

The subobject determines which Project Management object is transferred.

This configuration step is required for all SAP and non-SAP project systems.

  1. Select a groupimg for the main object link type (Main Object) and a grouping for the subobject link type (Subobject).
  2. Double-click Field Mapping.
  3. Select a Subobject Field Name.
  4. Select a Project Management Object.
  5. Select a Project Management Object Field Name.

This example describes the mapping of Project Management to Microsoft Project.

The main and subgroupings are defined as follows:

Main Group   Group   Description
PDMP   PDMP   MS Project Project Definition
PDMP   MAR   MS Project Role Link
PDMP   MAT   MS Project Task Link
PDMP   MR   MS Project Resource
PDMP   MT   MS Project Task

Mapping of header fields of a project in Project Management to header fields in Microsoft Project:

PDMP   Description   PDCP
FINISH_DATE   Project Finish   FINISH_DATE_FIX
NAME   Project Name/Description DESCRIPTION
START_DATE   Project Start   START_DATE_FIX

Mapping for all other objects can also be determined in this way.