Ansicht
Dokumentation

PPPI_MD_3332 - Define Shift Sequence

PPPI_MD_3332 - Define Shift Sequence

General Material Data   Fill RESBD Structure from EBP Component Structure  
This documentation is copyright by SAP AG.
SAP E-Book

In this step you define the following:

  • Grouping
Here you can create shift sequences and shift definitions for special areas (for example, different plants or different areas of a plant) and choose between resources when maintaining available capacity.
  • Work break schedule
Here you define the parameters that describe the individual work break schedules in more detail, for example:
  • Start

  • Finish

  • Break times

  • Shift definition
Here you define the parameters common to several resources that describe the individual shifts in more detail, for example:
  • Start

  • Finish

  • Break times

  • Validity period of a shift

The shift definition serves, depending on the resource type, the following purposes:

  • For resources at which a manufacturing process takes place, you use the shift definition to define a time-dependent available capacity.

  • For purely storage resources, you use the shift definition to determine time periods in which a volume-dependent or quantity-dependent available capacity changes.

In Logistics (LO) you can reference daily work schedules from the personnel system (HR). If you reference a daily work schedule in LO from HR and this is changed in HR, then this change will also directly affect the application in LO.
  • Shift sequences
You can assign the shift sequence of a capacity category as available capacity at the resource.
You define a sequence of shifts per weekday. The shift sequence shows a summary of the shift definitions.
In capacity planning the system uses the predefined values from the shift definition to determine the available capacity of a resource.
The system calculates the following values:
  • the capacity

  • the actual operating time for the capacity

The standard system contains settings for various shift sequences.

Define

  1. Grouping
  2. Work break schedules
  3. Shift definitions
  4. Shift sequences