PPPI_PO_355 - Define Shift Sequence

PPPI_PO_355 - Define Shift Sequence

Fill RESBD Structure from EBP Component Structure   RFUMSV00 - Advance Return for Tax on Sales/Purchases  
This documentation is copyright by SAP AG.
SAP E-Book

In this step, you define the following:

  • Shift sequences
You can assign the shift sequence of a capacity category as available capacity in the resource.
You define a sequence of shifts for each day of the week. The shift sequence shows a summary of shift definitions.
  • Shifts
Here you define the parameters for all resources that describe the individual shifts in more detail, such as:
  • Start

  • Finish

  • Break times

  • Validity period of a shift

In capacity planning, the SAP System uses the predefined values from the shift definition to determine the available capacity of a resource.
The following values are determined:
  • the capacity

  • the actual operating time of the capacity

  • Break models
Here, you define the parameters that describe the individual break models in more detail, such as:
  • Start

  • Finish

  • Break times

The standard delivery of the SAP System contains settings for various shift schedules.

Define the following:

  1. Shift schedules
  2. Shifts
  3. Break models