Define the budget relevance of overhead accounting (CO) business processes.

In this configuration activity, you can define a selection of CO business processes as non-budget relevant and override the budget relevance settings made for the affected G/L account master data (budget account).

Budget consumption is also influenced by the budget relevance settings made for the G/L accounts that are used as budget accounts. The combination of both settings produces the following budget relevance for CO postings:

Budget Account CO Process Line Item of Journal Entry
Not Bdgt-Relvt. Not Bdgt-Relvt. No Budget Consumption
Not Bdgt-Relvt. Bdgt-Relvt. No Budget Consumption
Bdgt-Relvt. Not Bdgt-Relvt. No Budget Consumption
Bdgt-Relvt. Bdgt-Relvt. Budget Consumption

Bdgt-Relvt.

Bdgt-Relvt.

SAP delivers the following CO process settings:

CO Business Process Key Budget-Relevant
Universal Allocation Cost Center Allocation ACAA No
Universal Allocation Cost Center Distribution ACAD Yes
Manual Cost Allocation (allocation of secondary costs) KAMV No
Actual Settlement (settlement to cost center or WBS element) KOAO No
Actual Settlement - external (settlement to assets) KOAE No
Actual Overhead - periodic KZPI No
Actual Activity Allocation (direct activity allocation including reposting) RKL No
Repost Costs (reposting of primary costs) RKU1 Yes
Repost Revenues RKU2 No

RKU2