SIMG_CFMENUOLPFOPKP - Define Production Scheduling Profile for Discrete Manufacturing
Fill RESBD Structure from EBP Component Structure RFUMSV00 - Advance Return for Tax on Sales/PurchasesThis documentation is copyright by SAP AG.
Create production scheduling profiles for specific plants.
In a production scheduling profile, you can:
- Specify that certain business transactions or processes are to be carried out in parallel in a production or process order
- Order release at the time the order is created
- Generation of document link from the material master when the order is created
- Generation of document link from a BOM when the order is created
- Printing at the time of order release
- Scheduling upon order release
- Generation of document link from the material master upon order release
- Generation of document link from a BOM upon order release
- Specify whether only partial quantities are to be confirmed at the time of an availability check
- Specify that an automatic goods receipt is to take place
- Specify an overall profile for capacity leveling
- Specify how the capacity requirements of the operations are to be taken into account in the basic load
- Specify when capacity scheduling is to be carried out in the capacity availability check
- Specify that in the case of the confirmation:
- No short quantities are to be updated
- No excess quantities are to be updated
- Neither short nor excess quantities are to be updated
- An adjustment of the operation and component quantities to the actual values is to take place
- Make various specifications in the area of batch management:
- Automatic batch creation when an order is opened
- Branching to batch classification when a batch is changed
- Extended batch classification via Customer Function Call
- Generation of a batch split record in the production order for each batch that is found
- Definition of a default date for the date of manufacture with possible offset
- Specify settings regarding transport:
- Specify that only transport requirements are to be created if transport requirements can be generated for all the components of the operation
- Specify that either the committed quantities or the required quantities are to be taken into account when transport requirements are generated
- Specify that the creation of transport requirements is to take place automatically
- Specify which order type is to be suggested depending on the business process
- Specify that the system is to adopt the best-before/shelf life expiration date (BBD/SLED) in the batch master after calculation of this date, or recalculate the BBD/SLED after a rescheduling.
You can assign a production scheduling profile to a:
- Material (Work Scheduling screen in material master)
- Production supervisor
The assignment to a material takes higher priority.
The production scheduling profile is adopted in the production or process order at the time the order is opened.
- Create the necessary production scheduling profiles.
- Assign the profiles to the appropriate materials or production supervisors.
Vendor Master (General Section) BAL_S_LOG - Application Log: Log header data