SIMG_CFMENUOLPKOPU3 - Define Scheduling Parameters for Production Orders
CL_GUI_FRONTEND_SERVICES - Frontend Services ROGBILLS - Synchronize billing plansThis documentation is copyright by SAP AG.
Define the parameters for scheduling production orders per plant, order type, and production supervisor.
This comprises maintaining
- date adjustment when dates are exceeded
- date control for detailed scheduling
- reduction
The parameters are described in what follows in details:
- In detailed scheduling you define:
- how production dates are to be calculated
- whether capacity requirements are generated
- In date adjustment you specify whether and how the basic dates are adjusted to the production dates (for example, when deadlines are exceeded) and how dates for dependent requirements are to lie.
- In Scheduling control for detailed scheduling you specify the control parameters for detailed scheduling, among other things the
- scheduling type
- Here you specify in which direction scheduling is to be carried out and whether it is to be carried out to an exact time. Among other things you can specify that a scheduling run only be used to generate capacity requirements.
- Start date in the past
- Here you specify how many days an order may lie in the past before today scheduling is triggered.
- Calculate dates automatically
- Here you specify whether scheduling is carried out automatically on saving.
- Display log automatically
- Here you specify whether the log is displayed automatically on scheduling.
- Required date of material
- Here you specify where the required date of a component should be with respect to an operation.
- Schedule exact to the break
- Here you specify that the exact time a break occurs must be taken into account.
- Dates to be specified
- Here you specify that when you create or change an order the user must enter schedules dates (production dates) instead of basic dates.
- Move order
- Here you specify whether the order can be moved if partially confirmed operations exist.
- In reduction you specify
- whether in the order or in the collective order all the operations are to be reduced or only those along the critical path.
- Reduction along the critical path is only possible for networks, production orders and planned orders with parallel sequences and for collective orders that contain production orders or planned orders.
- up to which maximum reduction level the reduction takes place
- to what percentage the float before and after production in every reduction level is to be reduced.
Define the scheduling parameters for production orders.