SIMG_CFMENUOPP1OMIY - Define Planning File Entries for Goods Movements

SIMG_CFMENUOPP1OMIY - Define Planning File Entries for Goods Movements

CL_GUI_FRONTEND_SERVICES - Frontend Services   TXBHW - Original Tax Base Amount in Local Currency  
This documentation is copyright by SAP AG.
SAP E-Book

Planning file entries are also created in inventory management. However, in the standard system, not all goods movements trigger a planning file entry.

A differentiation is made between materials that are planned using reorder point planning and other materials. For materials that are not planned using reorder point planning, the system always creates a planning file entry if no reference exists to a reservation (for example, an order). If such a reference does exist, a planning file entry is only created for the material, if:

  • More than the remaining open rest quantity is placed in stock or issued from stock.
  • Less than the remaining open rest quantity is placed in stock or issued from stock and the final delivery indicator is set.
  • The requirements date/receipt date of the reservation lies in the future (not valid for purchase orders).

You can also define tolerance values for the first two points. This means that a planning file entry is only created when the quantity deviation is greater than the specified tolerance value. You can define this customizing setting for individual plants.

For a material that is planned using reorder point planning, the system only creates a planning file entry if the stock level lies below the reorder point at the time of the goods receipt. In the case of a goods issue, a planning file entry is only created if the stock level falls below the reorder point after the goods issue.

You can also instruct the system to create a planning file entry for each goods movement.