SIMG_CFMENUOPP1OPPQ - Carry Out Overall Maintenance of Plant Parameters
General Material Data General Material DataThis documentation is copyright by SAP AG.
In this step, you can specify all plant parameters for the material requirements planning.
In addition, you receive an overview of the
When specifying the plant parameters, you have the following options:
- creating the MRP parameters for a new plant
- deleting the MRP parameters for a plant
- maintaining individual MRP parameters
- copying the MRP parameters of a plant already maintained into a new plant
You must specify the MRP parameters in this menu option if the following requirements are met:
- If you create the MRP parameters for a new plant for the first time
- If you completely want to delete the MRP parameters for a plant
Specify the planning parameters.