Ansicht
Dokumentation
SIMG_CFMENUORKKOKY6 - Check Valuation Variants for Cost Object ID
Fill RESBD Structure from EBP Component Structure General Data in Customer MasterThis documentation is copyright by SAP AG.
Here you create a
You create valuation strategies for the following objects:
- Material components
- Here you define the sequence in which the system searches for prices in the accounting view and the costing details screen of the material master record to valuate the materials.
- Internal activities
- Here you define the sequence in which the system searches for prices in activity type planning in cost center accounting to valuate the internal activities.
- You also specify what plan version in cost center accounting is used.
-
In Release 3.0 you can also valuate the internal activities with the actual activity prices in cost center accounting.
Strategy sequences
You define the individual valuation bases of the valuation variant as strategy sequences. For the valuation of the material components, for example, you define a strategy sequence that reads the fields in the material master record in the following sequence:
- Planned price 1
- Standard price
-
Moving average price
The first price that is not zero is used to valuate the material component. To be able to use the valuation variant in costing, you must assign the valuation variant to a costing variant.
- The standard system contains a number of predefined price strategies.
- Seventeen (17) price strategies are currently available for material valuation. You can select up to five strategies per valuation variant.
- Five price strategies are available for internal activities. You can select up up three activity prices per valuation variant.
- The standard system contains predefined valuation variants. You can modify these valuation variants to suit your requirements by changing the standard strategy sequences.
- Enter an alphanumeric key and a text for the new valuation variant.
- Define a valuation strategy for material components by entering up to five values as the search sequence.
- Define a valuation strategy for internal activities by entering up to three values as the search sequence and assigning an appropriate plan version in cost center accounting to this valuation variant.
- Assign the valuation variant to a costing variant.
Fill RESBD Structure from EBP Component Structure ROGBILLS - Synchronize billing plans
This documentation is copyright by SAP AG.
Length: 2960 Date: 20240523 Time: 213230 sap01-206 ( 45 ms )