SIMG_OLME_VC_T163G_A - Set Up Confirmation Control

SIMG_OLME_VC_T163G_A - Set Up Confirmation Control

CPI1466 during Backup   Fill RESBD Structure from EBP Component Structure  
This documentation is copyright by SAP AG.
SAP E-Book

Define the confirmation control keys and specify the confirmation sequence.

Preliminary note

Once you have set up the confirmation control facility in a production system, you should not make any changes to the relevant settings. Changes to the Customizing settings can lead to data inconsistencies in your system (e.g. incorrect MRP-relevant quantities).

In this step, you define confirmation control keys and specify the confirmation sequence.

  • Confirmation control key
    For PO items in respect of which confirmations are to be used, a confirmation key must be assigned.
Example
You can define a confirmation control key with just one confirmation category (e.g. shipping notification) and a confirmation control key covering several confirmation categories (order acknowledgment, loading confirmation, shipping notification).

  • Confirmation sequence
    With the confirmation sequence, you can specify the order in which the individual confirmations defined in a confirmation control key are expected and which confirmation categories are to be automatically monitored.
    In addition, you can specify for all confirmation categories whether they are for your information only or are also to be relevant to Materials Planning and Goods Receiving.
  1. Define the desired confirmation categories within a confirmation controlkey.
  2. Specify the confirmation sequence for the desired confirmation control keys and specify which confirmation categories are relevant to MaterialsPlanning and Goods Receiving.
  3. Specify the monitoring period In the Monitoring Period column andchoose the relevant reference date:
  • PO date plus monitoring period

  • Delivery date minus monitoring period

Example
If you enter the value '10' in the Monitoring Period column and 'delivery date minus monitoring period' in the Reference Date column, the system will select all items that have not yet been acknowledged or confirmed 10 days prior to the delivery date in the purchase order.
The items concerned are shown with the date in confirmation monitoring in Purchasing analyses.

Settings under 'Confirmation control keys'

  • Select whether an inbound delivery is to be created automatically for the predelivered purchasing documents
  • Select whether a goods receipt is to be created automatically
  • Define your own confirmation control keys by adding further entries to the table

Settings under 'Confirmation sequence'

In this step, you can do the following based on the previous selection:

  • Define the monitoring period
  • Define the reference date

Example
If you enter the value '10' in the Monitoring Period column and 'delivery date minus monitoring period' in the Reference Datecolumn, the system will select all items that have not yet been acknowledged or confirmed 10 days prior to the delivery date in the purchase order.
The items concerned are shown with the date in confirmation monitoring in Purchasing analyses.

Please NOTE:

  • Deletion option is not available
  • The following fields cannot be edited: MRP-Relevance, GR-Relevance, and
    GR Assignment