SIMG_OLPR_BKZ_OPS8 - Define Procurement Indicators for Material Components

SIMG_OLPR_BKZ_OPS8 - Define Procurement Indicators for Material Components

General Data in Customer Master   RFUMSV00 - Advance Return for Tax on Sales/Purchases  
This documentation is copyright by SAP AG.
SAP E-Book

In this step you can define procurement indicators for frequently used combinations of settings for procurement, so that you do not have to always enter these settings.

The indicator combines the following parameters:

  • The priority for plant stock, project stock, and sales order stock; this determines in which stock the components are kept.
  • Indicator for third party orders
  • Indicator for preliminary requirements
  • Item category

You can set a procurement indicator for every component in the component overview. Alternatively, you can define a default value in in the network profile. Once assigned, procurement indicators cannot be changed.

You often generate planned independent requirements, that is preliminary requirements for stock materials, whereby these are to be kept in project stock.

To do this you enter a purchase order indicator with priority 1 for project stock, set the preliminary requirements indicator and choose the item category L (stock item).