SIMG_OLPR_OPSB - Maintain Planning Profiles
ROGBILLS - Synchronize billing plans General Material DataThis documentation is copyright by SAP AG.
In this step, you:
- create new plan profiles
- change existing plan profiles
To be able to carry out project revenue planning, you must create a plan profile or use an existing one.
The following parameters are relevant to project cost planning:
- Time horizon
- Here, you define the following:
- period into the past, from the start year, for which you can plan
- period into the future, from the start year, for which you can plan
- cost planning start year
- planning of overall and/or annual values
- Value representation
- standard view displayed as well as the planned value when you access the function
- decimal places and scaling factor as default values
- Planning in all WBS elements or only in planning elements
- Bottom-up planning within structure-oriented planning
-
The indicator determines whether planning is by the bottom-up procedures:
If you set the indicator, the system automatically totals up the cost values each time you save and check them. The higher-level WBS element receives the total plan values for the WBS elements beneath it as its structure plan value.
You must first have processed the following menu items and parameters, so that they are available as default values:
- revenues
- Revenue elements are cost elements defined with cost element type 11.
- Use "Detail" to check the plan profiles delivered as standard in the SAP System.
- Change the details as necessary in the plan profiles, or create new ones as appropriate.
Additional information
You have the following alternative ways of assigning a plan profile to a project:
- as a default value in the Project System configuration menu
- in the project profile for a project definition (Operative structures)
- in the project profile for a standard project definition (Basic data)
- in the Project System application menu
- in the project definitioan control data, if you have not stored a plan profile in the project profile. (In the area menu, choose Operative structures -> Work breadown struc -> Change -> Detail -> Control -> Plan profile).