SIMG_OLPR_V_TECPPS - Define CO Versions for Easy Cost Planning
CL_GUI_FRONTEND_SERVICES - Frontend Services Fill RESBD Structure from EBP Component StructureThis documentation is copyright by SAP AG.
In this work step you determine which CO version you use for Easy Cost Planning
In the standard system the update of the calculated values from Easy Cost Planning is in CO version 000.
However if you use Easy Cost Planning for the preliminary costing of complex projects, you should use another CO version than 000 for updating the values.
Reason:
After preliminary costing the project starts with simultaneous costing using networks.The system can update data from network costing only in CO version 000.
To prevent the data from Easy Cost Planning and network costing interfering with each other, define a different CO version for updating the values from Easy Cost Planning.
- Enter the CO version that the system should use for updating costing data from Easy Cost Planning in the Version column.
- The input help (F4) displays all existing CO versions for the current controlling area..
- If you also want the system to update the planned revenues, set the Planned revenues indicator.