All the orders from a material staging area (interim zone) are served from a production line in production. The material staging process is order-related, but the components are not taken directly from the warehouse. The material requirement of a day is first taken from the warehouse and placed into an interim zone. Production takes the components required for the individual orders from this interim zone.

Transfer requirements are created for the individual orders. The components are defined as picking parts. All the transfer requirements for a planned date (day) and a production storage type (supply area) are grouped together using a group number. The components are taken on a cumulative basis from the warehouse using the 2-step picking procedure. Before the production department starts production, all the components for all orders of a day are placed into an interim zone. The individual orders request the components using the respective transfer requirements. The system posts the components from the interim zone to the individual orders.

To be able to use 2-step picking, you need the group number. This group number defines a multiple processing activitiy that groups several reference documents together (transfer requirements or deliveries).

  • In the SAP standard system, 2-step picking is not activated in warehouse number 001.
  • In warehouse number 001, storage type 200 is defined as an interim zone and movement type 850 for stock removals (picking).
  • In the storage type search, storage type 200 is defined for 2-step picking.

2-step picking is controlled for transfer requirements at warehouse number level. This control, however, is activated for the individual transfer types.

Set the parameters required for 2-step picking in the sequence specified.

  1. Control of transfer requirements:
    1. First activate 2-step picking globally for the transfer requirements in a warehouse number.
    2. Define whether 2-step picking is to be executed depending on the material. If control is material-dependent, the relevance of the material must be defined for each warehouse number in the material master.
  2. Transfer type control:
    1. You must activate 2-step picking explicitly for each transfer type since 2-step picking is only useful for certain transfer types. If you only want to use 2-step picking for certain stock removals, such as material staging for production, you must define a separate transfer type for the respective movement types.

You activate 2-step picking for deliveries in a separate step independently of the transfer requirements. For more information on this step, refer to the chapter "Shipping: 2-step picking".