Ansicht
Dokumentation
_ISPSFM_V_FMAVCL_ACT - Define Activation of Availability Control
General Material Data ROGBILLS - Synchronize billing plansThis documentation is copyright by SAP AG.
In this IMG activity, you activate availability control by assigning an activity status for each ledger and fiscal year (from year). You can choose between five activation statuses for each availability control ledger:
- Ledger not active
Posting values (including budget values) are not updated in the availability control ledger and no availability control takes place.
- Active without availability checks
Posting values are updated in the availability control ledger. No availability control takes place.
- Active with usual check logic
Posting values are updated in the availability control ledger. The usual availability control takes place. In the usual availability control, the error messages of AVC checks are always issued as warning messages if the available amount (= difference between the consumable budget and consumed amounts) is not reduced by the posting activity for each availability control object.
- Active with soft check logic
Posting values are updated in the availability control ledger and an availability control check is carried out. During this check, the system stops all AVC messages if the available amount for the availability control object is not reduced by the posting.
- Active with strict check logic for document chains
Posting values are updated in the availability control ledger. The usual availability control takes place, except for document chains. Strict availability control applies to document chains. This means that each document of a document chain is checked again and can be rejected by an error message of the availability control, even if the new document does not contain any additional budget consumption.
This means, for example, that the posting of an invoice must always undergo this strict check again even though availability control has already taken place for the commitment of the corresponding purchase order.
- Active with strict check logic
Posting values are updated in the availability ledger. All postings undergo the strict check logic. This strict check logic can also stop postings if the available amount of a control object is increased. This activation is only used in special situations.
SAP recommends that you use the normal check logic or the check logic with strict check for document chains.
In this activity you can also define whether you want to exclude revenue items from the availability control in the chosen Availability Control Ledger. Set indicator Ignore Revenue Items for this. In this case, budget values and commitment/actual values of revenue account assignments are neither checked nor updated in the availability control ledger.
You want to use the ledger 9H from the year 2002 without checks and only update values first. You want to use the ledger with availability checks from the fiscal year 2003.
You define the following settings for this:
Ledger | FYear | Status of AVC |
---|---|---|
9H | 2002 | Active without availability control |
9H | 2003 | Active with normal check logic |
Example of check logic for document chains
You selected the setting Active with strict check logic for document chains. The following tolerance limits are set in the tolerance profile for postings of the document chain purchase requisition -> purchase order -> invoice:
Activity group | Tolerance limit | Message type |
---|---|---|
20 (purchase requisition) | 120 % | warning |
30 (purchase order) | 110 % | warning |
40 (invoice) | 100 % | errors |
You create a purchase order of 230 that follows a corresponding purchase order and invoice with the same amount. The current consumable budget of the control object remains constant at 200 for all 3 postings. If the strict check logic for document chains is active, the system acts in the following way (example):
- The purchase order can be posted without a message ( the tolerance limit set is only exceeded by amounts >240)
- The purchase order can also be posted, but the system issues a warning (the tolerance limit is exceeded by amounts >220)
- The invoice posting cannot be posted, the system issues an error message (the tolerance limit is exceeded by amounts >200)
- In the usual check logic, the availability control would not reject the invoice posting in the last step because the invoice does not contain any additional budget consumption against the purchase order (the consumable amount on the affected control object stays the same) and because of this only a warning is issued instead of an error message.
You can only assign an activation status to an availability control ledger (and activate it) if you have defined all the settings required in the availability control IMG activities.
- Select an availability control ledger you want to use and a "from fiscal year" as well as an activation status for it.
- Save your entries.
Note that activating several AVC ledgers when using parallel availability controls influences performance. You should therefore not activate more than 3-4 AVC ledgers.
Carry out the Reconstruction of Availability Control after you have activated your AVC ledger.
You start the reconstruction of availability control in the Funds Management menu under Budgeting -> Tools -> Availability Control -> Reconstruct.
CPI1466 during Backup Fill RESBD Structure from EBP Component Structure
This documentation is copyright by SAP AG.
Length: 7492 Date: 20240523 Time: 154410 sap01-206 ( 117 ms )